It’s been three weeks since the first earth was turned on the extension. In this time, the plumbing’s been realigned, 80 cubic metres of soil removed, footings dug and laid and retaining walls erected. Things are running a little behind schedule on account of a week of rain, but other than that, it’s starting to take shape.

Here are the latest piccies.

164-backyard-before-extension-6-10-apr-07.JPG

163-extension-29-may-07-8.JPG

162-extn-12-jun-07.JPG

In the next fortnight, we should see the slab and frame in place. It’s really good to watch the jigsaw puzzle being put together and we have a newfound admiration for builders, their organisational skills and their problem solving abilities! There are so many moving pieces in a job like this!

Cheers,
Jason, Chrissy and the Girls